10 Differences Between pert and cpm

What is PERT?

PERT (Program Evaluation and Review Technique) is a project management technique used to analyze and represent the tasks and activities involved in completing a project. It was developed in the 1950s by the United States Navy to manage complex defense projects.

Examples of PERT

Let’s consider an example of building a new house. The tasks in the project could include designing the floor plan, obtaining permits, hiring contractors, construction, and inspections.

Uses of PERT

PERT is commonly used in projects with a large number of interrelated tasks and uncertainties, such as construction projects, research and development projects, and product development. It allows project managers to estimate project completion time, identify critical tasks, and allocate resources efficiently.

What is CPM?

CPM (Critical Path Method) is another project management technique used to analyze and represent the tasks and activities involved in completing a project. It was developed in the late 1950s by DuPont and Remington Rand corporations.

Examples of CPM

Let’s take the same example of building a new house. The tasks could include obtaining permits, clearing the site, laying the foundation, framing, plumbing, electrical work, insulation, drywall, painting, and finishing.

Uses of CPM

CPM is widely used in projects with well-defined tasks and known durations, such as construction projects, manufacturing processes, and event planning. It helps project managers identify the critical path, calculate project duration, schedule resources, and manage dependencies between tasks.

Differences Table

Difference Area PERT CPM
Nature of Projects Suited for projects with high uncertainty and non-repetitive tasks Ideal for projects with well-defined tasks and known durations
Time Estimation Probabilistic time estimates using three time estimates: optimistic, most likely, and pessimistic Deterministic time estimates based on historical data and expert opinions
Critical Path Does not focus on identifying critical path(s) Identifies the critical path(s) to determine project duration
Activity Dependency Allows for flexible and complex activity dependency relationships Relies on strict finish-to-start dependency relationships
Resource Management Does not consider resource availability or allocation Takes into account resource availability and allocation
Project Control Emphasizes control through in-depth analysis of project schedule, time variances, and probabilities Emphasizes control through monitoring project progress against a predetermined schedule
Application Domain Commonly used in research and development projects, product development, and projects with uncertain variables Widely used in construction projects, manufacturing processes, and projects with well-known variables
Task Dependency Account for both sequential and parallel task dependencies Primarily focus on sequential task dependencies
Complexity Handles projects with greater complexity and uncertain timelines Works best for projects with relatively simpler task relationships and predictable timelines
Statistical Analysis Utilizes statistical analysis to calculate project variance and probability distributions Does not involve statistical analysis, as it assumes deterministic task durations

Conclusion

In conclusion, PERT and CPM are project management techniques used to analyze and represent project activities. However, they differ in terms of project nature, time estimation methods, critical path identification, resource management, and project control. PERT is suitable for complex projects with uncertainties, while CPM is ideal for projects with well-defined tasks and known durations.

People Also Ask:

1. What is the main difference between PERT and CPM?

The main difference between PERT and CPM lies in the nature of projects they are best suited for. PERT is suitable for projects with high uncertainty and non-repetitive tasks, while CPM is ideal for projects with well-defined tasks and known durations.

2. How do PERT and CPM calculate project duration?

PERT calculates project duration by using probabilistic time estimates, considering the optimistic, most likely, and pessimistic estimates. On the other hand, CPM calculates project duration based on deterministic time estimates, relying on historical data and expert opinions.

3. Does PERT or CPM consider resource availability?

PERT does not consider resource availability or allocation. However, CPM takes into account resource availability and allocation while scheduling and managing project tasks.

4. In which domains are PERT and CPM commonly used?

PERT is commonly used in research and development projects, product development, and projects with uncertain variables. CPM, on the other hand, is widely used in construction projects, manufacturing processes, and projects with well-known variables.

5. Can PERT and CPM be used together?

Yes, PERT and CPM can be used together in project management. PERT can identify critical tasks and uncertainty, while CPM can determine the critical path and project duration. Combining both techniques can provide a comprehensive approach to project planning, scheduling, and control.